Case study 02 · New build · education · South-East England · £1m – £2m

A science block from a planning set, in two working days

A ground-up two-storey teaching and science block of roughly 445 m² GIA — light-gauge steel frame, two laboratories, PV roof, sloping site — priced from planning drawings and the contractor’s own costing notes, with the quote lines linked live to the drawing.

445 m²

GIA over two storeys

2 days

Brief to issued quote

27

Priced sections

105

Take-off items

The Brief

What arrived — and what didn’t.

Document Status Note
Planning application set Received 27 sheets at 1:100 and 1:200 on A3 — site, floor and roof plans, elevations, sections and a materials schedule.
The contractor’s own costing notes Received A hand-built take-off and costing brief. Adopted as the priced basis and then verified line by line against the drawings.
Draft project programme Received 42 activities over 39 weeks. Used to price preliminaries and site management week by week rather than as a percentage.
A cladding subcontractor’s quote and bill — from a different job Received Usable as a rate library only. It excluded scaffold, which mattered later.
Structural drawings Missing None. The foundation type was contradictory within the notes themselves.
Window schedule Missing Thirty windows counted off the elevations and carried as a stated provisional sum.
Ground investigation, M&E design, confirmed floor level Missing Geotechnical, SUDS and a raft allowance carried. Finished floor level flagged as a ±150 mm risk to the groundworks quantities.

The ask. A full quote ‘by the end of the week’, with the contractor’s own quantities respected in all respects. First email Thursday, supporting pack Friday, quote issued Monday.

Method

How it was measured and priced.

Template first, then price

A master template of roughly 1,870 lines was cloned and priced line by line, rather than a fresh list of items being invented. The first pass added 127 duplicate lines at section level and was thrown away; the second priced the template’s own lines.

Every rate source-tagged

Three comparable projects — a boathouse new-build, a primary-school nursery block and a third school’s mined actuals — plus the cladding bill and an in-house parametric £/m² model. Each line records where its rate came from.

Take-off linked to the quote, then deliberately unlinked

23 measurement groups, 105 items across five calibrated drawing pages, with quote lines linked live to the drawing metrics for counts. The area and linear links were then removed on purpose: the contractor’s measured quantities govern, and the drawing polygons must not silently override them.

Preliminaries off the client’s own programme

Site management, welfare, access and the 26-week on-site period were priced from the programme that arrived with the brief, not from a generic allowance.

Ground floor plan at 1:100 showing classroom, prep room, laboratory, hallway, entrance and plant room with measured areas
Ground floor as proposed, 1:100 — the planning-stage drawing the whole price was measured from.

What It Caught

The things that would have eaten the margin.

01

A contradictory foundation design

The costing notes list both a 300 mm raft slab and strip footings with block-and-beam.

How it was carried

Read as stepped strips with a suspended floor on the sloping site, with a raft allowance where the levels demand it — priced as the notes’ own lines plus the allowance, and put back to the design team to confirm.

02

A unit error

West elevation cladding was stated as 114 m³.

How it was carried

Taken as m², checked against the actual elevation extent, and flagged rather than quietly corrected.

03

A double-counted layer

230 m² of fireline board listed identically for both the ground and first floors.

How it was carried

Priced once, to the underside of the first floor, with the duplication noted. That single catch avoided a five-figure double count.

04

Scaffold excluded by the cladding subcontractor

The subcontractor’s bill — the only cladding rate source available — excluded access.

How it was carried

A scaffold and MEWP allowance carried in preliminaries, so the cladding rate was not silently short.

05

Site access on no drawing at all

A single line in the architect’s brief mentioned a temporary trackway around farm buildings.

How it was carried

Provisional sum carried, with the scope and length listed as a clarification to be confirmed.

06

Items raised in conversation but never drawn

Fume cupboards, battery storage, a second HRV unit per classroom and an SBEM A+ target.

How it was carried

Four priced options carried outside the total, so the base price stayed comparable with anything else the client was pricing against.

07

Thirty windows and no schedule

Counted off the elevations. No sizes, no specification, no performance requirement.

How it was carried

A stated provisional sum and a written request for the schedule — not a guessed rate dressed up as a measured one.

Delivered

What went into the tender pack.

A 27-section priced quote

Built on the contractor’s own master template so it slotted straight into their system. Roughly 1,870 lines, every priced line carrying a source tag.

The measured take-off on the drawing

Five calibrated pages, 23 groups and 105 items, with the count lines linked live to the quote.

Four priced options

Fume cupboards, battery storage, an HRV upgrade and SBEM A+ advisory — each stated outside the total.

A clarifications list with the hand-back

Window schedule, project number, foundation type and finished floor level: the four things the price genuinely depends on.

First floor plan as proposed, the second plate measured for the take-off
First floor as proposed — the second measured plate.
Take-off viewer showing classroom, prep and laboratory floor zones measured on the ground floor plan, each group summing live
The take-off viewer — each measurement group sums live, and every quantity carries its audit trail back to the drawing.

Outcome

Quote issued on day two. Awaiting the window schedule, the project number and confirmation of the foundation type — the three things the price still depends on. A volumetric competitor was already engaged on the scheme, which the contractor described as ‘not a level playing field’. No award recorded.

What We’d Say to the Next Contractor

Respect the client’s quantities in all respects — but read them. Three of the seven findings were inside their own notes.

Anonymised by design. Region and value band only — never a client, an address or a tender total. Drawings are reproduced with title blocks removed, and delivered packs are shown as blurred page mosaics so the scale and structure are visible and none of the content is legible.

Is there a package on your desk right now?

Send it and we will price it the same way. Two working days from the point we agree the basis, on your letterhead, with every assumption written down where your client can see it.